BOULEVARD SUITES | CONSTRUCTION UPDATE OCTOBER 2020

ANOTHER GREAT YEAR AT ZIMBALI!
15th Dec 2020

In the August Zimbali Lakes Construction update, we were excited to announce the commencement of the developments first top structure building, i.e. Boulevard Suites.  

The site had been filled with ±23 000m³ of soil in preparation for the top structure building and handed over to the Kuhle group for construction to commence.

There has been rapid movement on site, with the piling machinery arriving and drilling commencing as can be seen in the photos below taken on 8 September 2020.

Updated photos, taken on 30 September 2020 (below), confirms the rate at which the site is developing. Bulk sewer and stormwater installation are almost complete and all piles have been completed.  The transformation of the site is noteworthy.

In October we should see the pile caps completed along with the casting of the first-floor slab (weather dependant) with the mechanical plant being procured for the site. 

Practical completion is still on track for beginning Q3 2021 with Final completion anticipated at the end of Q3 2021. 

Boulevard Suites is 100% sold out! 